Question follow-through · 27206
Lower Thames Crossing: Construction
To ask the Secretary of State for Transport, what measures are in place to monitor the condition of local roads used by construction traffic associated with the Lower Thames Crossing a) before, b) during and c) after construction.
About this written question
A written question asks a government minister for information in writing. Parliament publishes the question and any answer.
- Answering body
- Department for Transport
- Tabled
- 3 Sept 2026
- Target answer date
- 7 Sept 2026
- Answer
- 9 Sept 2026 · 6 calendar days after tabling
Elapsed calendar days describe the record timeline, not whether Parliament considers an answer on time.
Votes on this topic
- Draft Climate Change Act 2008 (International Aviation and International Shipping) Regulations 2026 · 24 Jun 2026
These Commons divisions share a topic label. The question did not necessarily lead to a vote.
Recorded timeline
3 Sept 2026
Question tabled
To ask the Secretary of State for Transport, what measures are in place to monitor the condition of local roads used by construction traffic associated with the Lower Thames Crossing a) before, b) during and c) after construction.
7 Sept 2026
Target answer date
Date supplied by the official written-questions record.
9 Sept 2026
Answer published
National Highways has assessed the potential impacts of the Lower Thames Crossing on the road network during construction, including on local roads in South Basildon and East Thurrock. The assessment is set out in Chapter 8 of the Transport Assessment and...
Official data retrieved 1 Oct 2026.
Later records
Possible follow-up questions
Strong links require the same MP, department and exact heading. Other same-department questions are shown as unreviewed candidates, not as confirmed follow-ups. No debate link is asserted unless a stable source relationship exists.
No later same-department questions indexed.
This is an absence in covered public data, not evidence that no follow-up occurred elsewhere.