Question follow-through · 15448

Anglo Portuguese School of London: Construction

To ask the Secretary of State for Education, what steps her Department is taking to speed up the completion of building works at the Anglo Portuguese School of London; and if she will ensure that key facilities, including the play deck and kitchen, are co

answeredDepartment for Education

About this written question

A written question asks a government minister for information in writing. Parliament publishes the question and any answer.

Answering body
Department for Education
Tabled
2 Jul 2026
Target answer date
7 Jul 2026
Answer
7 Jul 2026 · 5 calendar days after tabling

Elapsed calendar days describe the record timeline, not whether Parliament considers an answer on time.

Recorded timeline

  1. 2 Jul 2026

    Question tabled

    To ask the Secretary of State for Education, what steps her Department is taking to speed up the completion of building works at the Anglo Portuguese School of London; and if she will ensure that key facilities, including the play deck and kitchen, are co

  2. 7 Jul 2026

    Target answer date

    Date supplied by the official written-questions record.

  3. 7 Jul 2026

    Answer published

    The department is aware of significant disruption for the Anglo Portuguese School of London and its pupils since the original contractor entered administration. A new contractor, Kier, was quickly appointed but identified various issues which needed to be...

Open official record

Official data retrieved 28 Sept 2026.

Later records

Possible follow-up questions

Strong links require the same MP, department and exact heading. Other same-department questions are shown as unreviewed candidates, not as confirmed follow-ups. No debate link is asserted unless a stable source relationship exists.

No later same-department questions indexed.

This is an absence in covered public data, not evidence that no follow-up occurred elsewhere.