River Thames: Flood Control

To ask the Secretary of State for Environment, Food and Rural Affairs, what the planned timetable is for the submission of the Development Consent Order for the River Thames Scheme.

answeredDepartment for Environment, Food and Rural Affairs

About this written question

A written question asks a government minister for information in writing. Parliament publishes the question and any answer.

Answering body
Department for Environment, Food and Rural Affairs
Tabled
15 Jun 2026
Target answer date
18 Jun 2026
Answer
25 Jun 2026 · 10 calendar days after tabling

Elapsed calendar days describe the record timeline, not whether Parliament considers an answer on time.

Votes on this topic

These Commons divisions share a topic label. The question did not necessarily lead to a vote.

Recorded timeline

  1. 15 Jun 2026

    Question tabled

    To ask the Secretary of State for Environment, Food and Rural Affairs, what the planned timetable is for the submission of the Development Consent Order for the River Thames Scheme.

  2. 18 Jun 2026

    Target answer date

    Date supplied by the official written-questions record.

  3. 25 Jun 2026

    Answer published

    The Environment Agency is progressing the River Thames Scheme following the reset, with an updated Outline Business Case which will be submitted in summer 2026. The programme timeline for the Development Consent Order and Construction phases will be agree...

Open official record

Official data retrieved 28 Sept 2026.

Later records

Possible follow-up questions

Strong links require the same MP, department and exact heading. Other same-department questions are shown as unreviewed candidates, not as confirmed follow-ups. No debate link is asserted unless a stable source relationship exists.

No later same-department questions indexed.

This is an absence in covered public data, not evidence that no follow-up occurred elsewhere.