Question follow-through · 9540

Future Combat Air System: Expenditure

To ask the Secretary of State for Defence, what is the total spend to date on the Tempest project, including pre-concept and early concept phases.

answeredMinistry of Defence

About this written question

A written question asks a government minister for information in writing. Parliament publishes the question and any answer.

Answering body
Ministry of Defence
Tabled
15 Jun 2026
Target answer date
17 Jun 2026
Answer
24 Jun 2026 · 9 calendar days after tabling

Elapsed calendar days describe the record timeline, not whether Parliament considers an answer on time.

Votes on this topic

These Commons divisions share a topic label. The question did not necessarily lead to a vote.

Recorded timeline

  1. 15 Jun 2026

    Question tabled

    To ask the Secretary of State for Defence, what is the total spend to date on the Tempest project, including pre-concept and early concept phases.

  2. 17 Jun 2026

    Target answer date

    Date supplied by the official written-questions record.

  3. 24 Jun 2026

    Answer published

    Since its inception, the UK Government has invested over £2 billion on the Future Combat Air System (FCAS) Tempest project. In addition to this, the project has attracted over £700 million of private investment since the programme began.

Open official record

Official data retrieved 28 Sept 2026.

Later records

Possible follow-up questions

Strong links require the same MP, department and exact heading. Other same-department questions are shown as unreviewed candidates, not as confirmed follow-ups. No debate link is asserted unless a stable source relationship exists.

No later same-department questions indexed.

This is an absence in covered public data, not evidence that no follow-up occurred elsewhere.