Question follow-through · 5326

Free Schools

To ask the Secretary of State for Education, what her planned timeline is for the delivery of new free schools approved in principle, including the (a) key stages from approval to opening, (b) typical duration of each stage and (c) factors impacting deliv

answeredDepartment for Education

About this written question

A written question asks a government minister for information in writing. Parliament publishes the question and any answer.

Answering body
Department for Education
Tabled
1 Jun 2026
Target answer date
3 Jun 2026
Answer
9 Jun 2026 · 8 calendar days after tabling

Elapsed calendar days describe the record timeline, not whether Parliament considers an answer on time.

Recorded timeline

  1. 1 Jun 2026

    Question tabled

    To ask the Secretary of State for Education, what her planned timeline is for the delivery of new free schools approved in principle, including the (a) key stages from approval to opening, (b) typical duration of each stage and (c) factors impacting deliv

  2. 3 Jun 2026

    Target answer date

    Date supplied by the official written-questions record.

  3. 9 Jun 2026

    Answer published

    New free school projects that are centrally delivered by the department typically progress through six key stages: pre‑feasibility (including finding a suitable site), feasibility, procurement, design and planning, construction and handover, and post‑comp...

Open official record

Official data retrieved 28 Sept 2026.

Later records

Possible follow-up questions

Strong links require the same MP, department and exact heading. Other same-department questions are shown as unreviewed candidates, not as confirmed follow-ups. No debate link is asserted unless a stable source relationship exists.

No later same-department questions indexed.

This is an absence in covered public data, not evidence that no follow-up occurred elsewhere.