Question follow-through · 126442
East Suffolk Line: Standards
To ask the Secretary of State for Transport, whether her Department has made an assessment of the potential impact of freight operations associated with Sizewell C on (a) passenger capacity, (b) journey times and (c) service frequency on the East Suffolk
About this written question
A written question asks a government minister for information in writing. Parliament publishes the question and any answer.
- Answering body
- Department for Transport
- Tabled
- 10 Apr 2026
- Target answer date
- 16 Apr 2026
- Answer
- 22 Apr 2026 · 12 calendar days after tabling
Elapsed calendar days describe the record timeline, not whether Parliament considers an answer on time.
Recorded timeline
10 Apr 2026
Question tabled
To ask the Secretary of State for Transport, whether her Department has made an assessment of the potential impact of freight operations associated with Sizewell C on (a) passenger capacity, (b) journey times and (c) service frequency on the East Suffolk
16 Apr 2026
Target answer date
Date supplied by the official written-questions record.
22 Apr 2026
Answer published
The train operator Greater Anglia is aware that freight traffic in relation to the constructions of Sizewell C is likely to increase in the future. Network Rail will continue to work closely with operators to assess how best to accommodate the additional ...
Official data retrieved 28 Sept 2026.
Later records
Possible follow-up questions
Strong links require the same MP, department and exact heading. Other same-department questions are shown as unreviewed candidates, not as confirmed follow-ups. No debate link is asserted unless a stable source relationship exists.
No later same-department questions indexed.
This is an absence in covered public data, not evidence that no follow-up occurred elsewhere.