Railways: North of England
To ask the Secretary of State for Transport, whether she has considered the potential merits of including the York Area Capacity Scheme works in the TransPennine Route Upgrade.
About this written question
A written question asks a government minister for information in writing. Parliament publishes the question and any answer.
- Answering body
- Department for Transport
- Tabled
- 19 Mar 2026
- Target answer date
- 26 Mar 2026
- Answer
- 26 Mar 2026 · 7 calendar days after tabling
Elapsed calendar days describe the record timeline, not whether Parliament considers an answer on time.
Votes on this topic
- Draft Climate Change Act 2008 (International Aviation and International Shipping) Regulations 2026 · 24 Jun 2026
These Commons divisions share a topic label. The question did not necessarily lead to a vote.
Recorded timeline
19 Mar 2026
Question tabled
To ask the Secretary of State for Transport, whether she has considered the potential merits of including the York Area Capacity Scheme works in the TransPennine Route Upgrade.
26 Mar 2026
Target answer date
Date supplied by the official written-questions record.
26 Mar 2026
Answer published
A decision to pause activity on the York Area Capacity and Performance Project was taken at the Spending Review. The decision was only taken after appropriate consideration of the project’s benefits and its interdependencies with other programmes of activ...
Official data retrieved 28 Sept 2026.
Later records
Possible follow-up questions
Strong links require the same MP, department and exact heading. Other same-department questions are shown as unreviewed candidates, not as confirmed follow-ups. No debate link is asserted unless a stable source relationship exists.
No later same-department questions indexed.
This is an absence in covered public data, not evidence that no follow-up occurred elsewhere.