Question follow-through · 59834
South West Main Line: Dawlish
To ask the Secretary of State for Transport, pursuant to the Answer of 13 January 2025 on Question 21418 on South West Mainline: Dawlish, whether she plans to provide funding for phase 5 of the Dawlish south west rail resilience fund.
About this written question
A written question asks a government minister for information in writing. Parliament publishes the question and any answer.
- Answering body
- Department for Transport
- Tabled
- 13 Jun 2025
- Target answer date
- 17 Jun 2025
- Answer
- 18 Jun 2025 · 5 calendar days after tabling
Elapsed calendar days describe the record timeline, not whether Parliament considers an answer on time.
More questions by this MP on Transport
- South West Main Line: Dawlish · 19 Jun 2025
- South West Main Line: Finance · 19 Jun 2025
- Cross Country Trains: Contracts · 23 Jun 2025
- Cross Country Trains: Standards · 23 Jun 2025
- Cross Country Line: Overcrowding · 23 Jun 2025
Shared topic keywords suggest a connection; they do not establish a follow-up.
Votes on this topic
- Draft Climate Change Act 2008 (International Aviation and International Shipping) Regulations 2026 · 24 Jun 2026
These Commons divisions share a topic label. The question did not necessarily lead to a vote.
Recorded timeline
13 Jun 2025
Question tabled
To ask the Secretary of State for Transport, pursuant to the Answer of 13 January 2025 on Question 21418 on South West Mainline: Dawlish, whether she plans to provide funding for phase 5 of the Dawlish south west rail resilience fund.
17 Jun 2025
Target answer date
Date supplied by the official written-questions record.
18 Jun 2025
Answer published
Following the Chancellors’s statement on 11 June we are now working to confirm our wider portfolio of rail enhancements, which will be published as part of the government’s commitment to set out its overall infrastructure pipeline.
Official data retrieved 28 Sept 2026.
Later records
Possible follow-up questions
Strong links require the same MP, department and exact heading. Other same-department questions are shown as unreviewed candidates, not as confirmed follow-ups. No debate link is asserted unless a stable source relationship exists.
South West Main Line: Dawlish
19 Jun 2025 · To ask the Secretary of State for Transport, pursuant to the Answer of 18 June 2025 to Question 59834 on South West Main Line: Dawlish, if she will set out a timescale for when a decision on whether Stage Five of the rail resilience programme for Dawlish
South West Main Line: Finance
19 Jun 2025 · To ask the Secretary of State for Transport, whether she plans to provide funding for the final phase of the South West Rail Resilience Programme.
Cross Country Trains: Contracts
23 Jun 2025 · To ask the Secretary of State for Transport, if she will make an assessment of the potential merits of ending cross-country train contracts early.
Cross Country Trains: Standards
23 Jun 2025 · To ask the Secretary of State for Transport, what discussions she has had with Crosscountry trains on the performance of its services.
Cross Country Line: Overcrowding
23 Jun 2025 · To ask the Secretary of State for Transport, what information her Department holds on the proportion of Crosscountry rail services that were overcrowded in each of the last 12 months.
South West Main Line: Dawlish
30 Jun 2025 · To ask the Secretary of State for Transport, pursuant to the Answer of 27 June 2025 to Question 61272 on South West Main Line: Dawlish, which rail enhancement projects will be funded by the Spending Review 2025.
Parking: Pedestrian Areas
30 Jun 2025 · To ask the Secretary of State for Transport, if she will take steps to help tackle pavement parking in Devon.
South West Main Line: Devon
9 Jul 2025 · To ask the Secretary of State for Transport, if she will publish her Department's analysis of phase 5 of the South West Rail Resilience Programme.
South West Main Line: Devon
9 Jul 2025 · To ask the Secretary of State for Transport, whether her Department has taken steps with Network Rail to develop a proposal for the Teignmouth to Parsons Tunnel section of the South West Rail Resilience Programme since the Spending Review 2025.
South West Main Line: Devon
9 Jul 2025 · To ask the Secretary of State for Transport, whether her Department commissioned an independent assessment of the viability of proposed engineering solutions for Phase 5 of the South West Rail Resilience Programme (a) during and (b) since the Spending Rev
South West Main Line: Devon
9 Jul 2025 · To ask the Secretary of State for Transport, what steps her Department plans to take to improve resilience along the stretch between Parsons Tunnel and Teignmouth pending the completion of Phase 5.
South West Main Line: Devon
9 Jul 2025 · To ask the Secretary of State for Transport, under what circumstances Phase 5 of the South West Rail Resilience Programme would receive funding.