James Cartlidge MP: written questions

4 Jul 2024–3 Jul 2025

How these years work

Our reporting years run from 4 July to 3 July, starting with the 2024 general election. They are not official parliamentary sessions. Office costs keep IPSA’s April–March financial years. Records may cover only part of a year; a missing record does not mean no work was done.

Read what this MP said, asked and contributed in Parliament.

7 published records · newest first.

Written questions

  • National Grid: East of EnglandDepartment for Energy Security and Net ZeroTabled 4 Mar 2025AnsweredUIN 35333More

    Question: To ask the Secretary of State for Energy Security and Net Zero, if (a) his Department and (b) Ofgem will make an estimate of the cost of the (i) sealing end compounds and (ii) other costs associated with the construction of the (A) underground and (B) oth

    Answer: It is the responsibility of the developers of electricity network projects – in this case National Grid Electricity Transmission (NGET) - to propose the route and obtain planning permission for that route. NGET presented cost estimates for the Norwich to ...

    Answered 7 Mar 2025

    Original Parliament record
  • National Grid: ConstructionDepartment for Energy Security and Net ZeroTabled 13 Jan 2025AnsweredUIN 23388More

    Question: To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 5 December 2024 to Question 17189 on National Grid: Costs of the Western and Eastern Links, if he will make an estimate of the time for delivering the onshore option

    Answer: At the time of Ofgem’s decision for Eastern Green Link (EGL) 1&2 Final Need Case, an onshore option was expected to be delivered by 2036, based on information provided by the Transmission Owner, National Grid Electricity Transmission. It was not inclu...

    Answered 16 Jan 2025

    Original Parliament record
  • National Grid: CostsDepartment for Energy Security and Net ZeroTabled 2 Dec 2024AnsweredUIN 17189More

    Question: To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 26 November 2024 to Question 16211 on National Grid: Costs of the Western and Eastern Links, whether (a) he and (b) Ofgem is able to provide the estimate requested.

    Answer: The analysis of an onshore reinforcement (i.e. overhead pylons) for Western Green Link was conducted 16 years ago and cost estimates for alternative options are not available.As the option of an onshore reinforcement for Eastern Green Link 1&2 did not...

    Answered 5 Dec 2024

    Original Parliament record
  • National GridDepartment for Energy Security and Net ZeroTabled 26 Nov 2024AnsweredUIN 16211More

    Question: To ask the Secretary of State for Energy Security and Net Zero, if he will make an estimate of the cost of building (a) the Western link and (b) all current and future stages of the Eastern Link if that route was primarily overland via pylons instead of o

    Answer: Ofgem reviews proposed project costs and ensures that network companies spend efficiently. Electricity network reinforcements are only approved where they are in the interests of consumers and help reduce system costs. Ofgem identified a net lifetime bene...

    Answered 29 Nov 2024

    Original Parliament record
  • National Grid: East of EnglandDepartment for Energy Security and Net ZeroTabled 9 Oct 2024AnsweredUIN 8177More

    Question: To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 8 October to Question 5072 on National Grid: Costs, what estimate he has made of the potential impact on consumer energy bills of the lifetime costs of delivering th

    Answer: As part of the feasibility work for the coordination proposal explored through the Offshore Coordination Support Scheme, independent analysis by Arup and the Electricity System Operator (now the National Energy System Operator) identified an increase in d...

    Answered 18 Oct 2024

    Original Parliament record
  • National Grid: CostsDepartment for Energy Security and Net ZeroTabled 10 Sept 2024AnsweredUIN 5072More

    Question: To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 10 September 2024 to Question 4389 on National Grid: Costs, whether (a) he and (b) Ofgem is able to provide the estimate requested.

    Answer: New network infrastructure is essential to meet the rising demand for electricity and connect new renewable generation. Ofgem estimates that the Western Link and Eastern Green Link will increase consumer bills by an average of £6.50 per annum over a 60-ye...

    Answered 8 Oct 2024

    Original Parliament record
  • National Grid: CostsDepartment for Energy Security and Net ZeroTabled 5 Sept 2024AnsweredUIN 4389More

    Question: To ask the Secretary of State for Energy Security and Net Zero, if he will make an estimate of the potential impact on consumer energy bills of the total lifetime cost of delivering (a) the Western Link and (b) all current and future stages of the Eastern

    Answer: Electricity network reinforcements are only approved where they are in the interests of consumers and help reduce overall system costs. For both the Western Link and the Eastern Green Link projects, decisions to proceed were based on robust cost-benefit a...

    Answered 10 Sept 2024

    Original Parliament record
Explore activity by topic or department

Written questions by answering department

4 Jul 2024–3 Jul 2025. One record per UIN and tabled date; the named department is not a measure of answer quality.

View as listCabinet Office: 10Cabinet Office10Department for Business and Trade: 11Department for Business and Trade11Department for Culture, Media and Sport: 11Department for Culture, Media a…11Department for Education: 7Department for Education7Department for Energy Security and Net Zero: 7Department for Energy Security …7Department for Environment, Food and Rural Affairs: 31Department for Environment, Foo…31Department for Science, Innovation and Technology: 2Department for Science, Innovat…2Department for Transport: 12Department for Transport12Department for Work and Pensions: 1Department for Work and Pensions1Department of Health and Social Care: 17Department of Health and Social…17Foreign, Commonwealth and Development Office: 16Foreign, Commonwealth and Devel…16Home Office: 4Home Office4Ministry of Defence: 1548Ministry of Defence1548Ministry of Housing, Communities and Local Government: 17Ministry of Housing, Communitie…17Ministry of Justice: 2Ministry of Justice2Prime Minister: 1Prime Minister1Treasury: 65Treasury65
What this shows and doesn't show
4 Jul 2024–3 Jul 2025. One record per UIN and tabled date; the named department is not a measure of answer quality. Published records do not measure effort or effectiveness. Methodology.
Department or topicPublished records
Cabinet Office10
Department for Business and Trade11
Department for Culture, Media and Sport11
Department for Education7
Department for Energy Security and Net Zero7
Department for Environment, Food and Rural Affairs31
Department for Science, Innovation and Technology2
Department for Transport12
Department for Work and Pensions1
Department of Health and Social Care17
Foreign, Commonwealth and Development Office16
Home Office4
Ministry of Defence1548
Ministry of Housing, Communities and Local Government17
Ministry of Justice2
Prime Minister1
Treasury65