Claire Young MP: written questions
4 Jul 2026–16 Oct 2026 · year in progress
How these years work
Our reporting years run from 4 July to 3 July, starting with the 2024 general election. They are not official parliamentary sessions. Office costs keep IPSA’s April–March financial years. Records may cover only part of a year; a missing record does not mean no work was done.
Read what this MP said, asked and contributed in Parliament.
5 published records · newest first.
Written questions
M49Department for TransportTabled 8 Sept 2026AnsweredUIN 28241More
Question: To ask the Secretary of State for Transport, whether National Highways has referred, or intends to refer, the dispute over defects identified at the M49 Severnside junction 1 to adjudication under the dispute resolution provisions of its construction cont
Answer: National Highways is continuing to engage with the principal contractor to seek an amicable and timely resolution to the issues identified at M49 Severnside Junction 1. As these discussions continue, no decision has been made on whether to pursue adjudica...
Answered 14 Sept 2026
Original Parliament recordM49Department for TransportTabled 8 Sept 2026AnsweredUIN 28192More
Question: To ask the Secretary of State for Transport, whether the contract awarded by National Highways for the construction of the M49 junction 1 at Severnside was let as a design and build contract or as a construction only contract; and whether responsibility f
Answer: National Highways is continuing to engage with the principal contractor to seek an amicable and timely resolution to the issues identified at M49 Severnside Junction 1. As these discussions continue, no decision has been made on whether to pursue adjudica...
Answered 14 Sept 2026
Original Parliament recordM49Department for TransportTabled 8 Sept 2026AnsweredUIN 28191More
Question: To ask the Secretary of State for Transport, whether the contract awarded by National Highways for the M49 junction 1 at Severnside was let on a fixed price basis or on a basis under which the final sum payable to the contractor could vary; and what the (
Answer: National Highways is continuing to engage with the principal contractor to seek an amicable and timely resolution to the issues identified at M49 Severnside Junction 1. As these discussions continue, no decision has been made on whether to pursue adjudica...
Answered 14 Sept 2026
Original Parliament recordM49Department for TransportTabled 8 Sept 2026AnsweredUIN 28190More
Question: To ask the Secretary of State for Transport, whether sums have been paid to the contractor for the M49 junction 1 at Severnside in addition to the original contract value in respect of variations, compensation events or claims.
Answer: The Department for Transport has indicated that it will not be possible to answer this question within the usual time period. An answer is being prepared and will be provided as soon as it is available.
Answered 11 Sept 2026
Original Parliament recordM49Department for TransportTabled 8 Sept 2026AnsweredUIN 28189More
Question: To ask the Secretary of State for Transport, what provisions the contract for the M49 junction 1 at Severnside contained requiring the contractor to remedy defects at its own cost; and whether National Highways has sought to recover any sums from the cont
Answer: National Highways is continuing to engage with the principal contractor to seek an amicable and timely resolution to the issues identified at M49 Severnside Junction 1. As these discussions continue, no decision has been made on whether to pursue adjudica...
Answered 14 Sept 2026
Original Parliament record
Explore activity by topic or department
Written questions by answering department
4 Jul 2026–16 Oct 2026. One record per UIN and tabled date; the named department is not a measure of answer quality.