Ben Obese-Jecty MP: written questions

Written questions by answering department

4 Jul 2026–13 Oct 2026. One record per UIN and tabled date; the named department is not a measure of answer quality.

View as listCabinet Office: 36Cabinet Office36Department for Business, Innovation, Science and Trade: 18Department for Business, Innova…18Department for Culture, Media and Sport: 1Department for Culture, Media a…1Department for Digital, Culture, Media and Sport: 4Department for Digital, Culture…4Department for Education: 8Department for Education8Department for Energy Security and Net Zero: 7Department for Energy Security …7Department for Environment, Food and Rural Affairs: 34Department for Environment, Foo…34Department for Science, Innovation and Technology: 1Department for Science, Innovat…1Department for Transport: 27Department for Transport27Department for Work and Pensions: 5Department for Work and Pensions5Department of Health and Social Care: 26Department of Health and Social…26Foreign, Commonwealth and Development Office: 12Foreign, Commonwealth and Devel…12Home Office: 52Home Office52Ministry of Defence: 689Ministry of Defence689Ministry of Housing, Communities and Local Government: 11Ministry of Housing, Communitie…11Ministry of Justice: 91Ministry of Justice91Northern Ireland Office: 2Northern Ireland Office2Treasury: 18Treasury18
What this shows and doesn't show
4 Jul 2026–13 Oct 2026. One record per UIN and tabled date; the named department is not a measure of answer quality. Published records do not measure effort or effectiveness. Methodology.
Department or topicPublished records
Cabinet Office36
Department for Business, Innovation, Science and Trade18
Department for Culture, Media and Sport1
Department for Digital, Culture, Media and Sport4
Department for Education8
Department for Energy Security and Net Zero7
Department for Environment, Food and Rural Affairs34
Department for Science, Innovation and Technology1
Department for Transport27
Department for Work and Pensions5
Department of Health and Social Care26
Foreign, Commonwealth and Development Office12
Home Office52
Ministry of Defence689
Ministry of Housing, Communities and Local Government11
Ministry of Justice91
Northern Ireland Office2
Treasury18

689 published records · newest first.

Written questions

  • AWE BurghfieldMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23311More

    Question: To ask the Secretary of State for Defence, what is the cost estimate to deliver to AWE Burghfield.

    Answer: While it is not clear which costs the Hon. Member is referring to, I can confirm that the latest cost estimate of delivering the MENSA programme at AWE Burghfield is £3.6 billion.

    Answered 8 Sept 2026

    Original Parliament record
  • TanksMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23310More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Armour Main Battle Tank Programme, how much has been spent so far on the progr

    Answer: As at July 2026, the Armour Main Battle Tank Programme had spent approximately £705 million. Against the published Whole Life Cost of £1,944.09 million in the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025-2...

    Answered 8 Sept 2026

    Original Parliament record
  • Guided WeaponsMinistry of DefenceTabled 28 Aug 2026Awaiting answerUIN 23309More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Brimstone 3, when does he expect to receive endorsement of the revised program

    Answer: No published answer in this record yet.

    Original Parliament record
  • SkynetMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23308More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, SKYNET 6 (aka FBLOS), whether supplier performance delayed the delivery of the

    Answer: There are many reasons for the delay in the build of SKYNET 6A, the first SKYNET 6 satellite – the first of type ever built in the UK. The main ones relate to the impact of the Covid restrictions, the sequestration by the US Government of some key US supp...

    Answered 8 Sept 2026

    Original Parliament record
  • Astute Class SubmarinesMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23307More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Astute Boats 1-7, whether delays have impacted the in-water phase for Boat 6.

    Answer: In September 2025, the sixth Astute Class submarine, HMS AGAMEMNON was commissioned into the Royal Navy and is undertaking the final stages of her in-water commissioning, before a handover to the Royal Navy to undertake sea trials. Achilles, the seventh a...

    Answered 8 Sept 2026

    Original Parliament record
  • WarshipsMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23306More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Multi Role Strike Ship, what is the status of the programme.

    Answer: The Defence Investment Plan confirmed that the Multi-Role Strike Ship programme would not be pursued and directed a shift in approach centred on the Amphibious Transport Ship. This reflects the Royal Navy’s developing Hybrid Navy concept and future Comman...

    Answered 8 Sept 2026

    Original Parliament record
  • Unmanned Air SystemsMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23305More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Protector, what progress he has made in solving the weapon testing delays.

    Answer: Previous delays have been overcome through a revised plan of combined USA and UK based testing, with final elements of safe separation trials concluding in the USA in June 2026 and further UK testing being conducted in August 2026. Paveway IV has been ope...

    Answered 8 Sept 2026

    Original Parliament record
  • Challenger TanksMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23304More

    Question: To ask the Secretary of State for Defence, what assessment has he made of the potential merits of equipping Challenger 3 with a hard-kill Counter-UAS active protection system.

    Answer: Challenger 3 is being equipped with a hard-kill Active Protection System as part of its planned survivability enhancements. The Department continues to assess emerging Counter-UAS capabilities and technologies across the force structure to ensure Army pla...

    Answered 8 Sept 2026

    Original Parliament record
  • ArtilleryMinistry of DefenceTabled 28 Aug 2026Awaiting answerUIN 23300More

    Question: To ask the Secretary of State for Defence, what assessment has he made of the availability of spares for the L118 105mm Light Gun.

    Answer: No published answer in this record yet.

    Original Parliament record
  • Armoured Fighting VehiclesMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23282More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Mechanised Infantry Programme, what assessment he has made of the potential im

    Answer: The reduction in the Mechanised Infantry Programme Whole Life Cost reported in the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025-26 reflects Defence Investment Plan outcomes and Army reprioritisation decisi...

    Answered 8 Sept 2026

    Original Parliament record
  • SubmarinesMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23281More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Submarine Dismantling Project, what is the nature of the unforeseen challenges

    Answer: The matters identified in the National Infrastructure and Service Transformation Authority (NISTA) Major Projects Annual Report relate to the complexities inherent in delivering a first-of-class submarine recycling project including the technical, plannin...

    Answered 7 Sept 2026

    Original Parliament record
  • NavyMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23280More

    Question: To ask the Secretary of State for Defence, whether his department has submitted the NSIGN Subs Full Business Case.

    Answer: The Naval Support Integrated Global Network (NSIGN) Submarine Support Full Business Case is currently progressing through the Ministry of Defence approvals process. As with all major defence business cases, approval is subject to the completion of the Dep...

    Answered 8 Sept 2026

    Original Parliament record
  • NavyMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23279More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Naval Support Integrated Global Network programme, following the publication o

    Answer: The Naval Support Integrated Global Network (NSIGN) programme continues to progress, with risk substantially addressed or actively managed through established processes. The reduction in reported Whole Life Cost reflects updated assumptions on scope, deli...

    Answered 8 Sept 2026

    Original Parliament record
  • Ministry of Defence: Civil ServantsMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23272More

    Question: To ask the Secretary of State for Defence, how many civil service posts across the Ministry of Defence are currently being filled by service personnel owing to the civil service recruitment freeze.

    Answer: The Ministry of Defence operates locally led recruitment controls and workforce deployment decision making. This enables business areas to recruit to Civil Service posts where justified by business need, aligned with Departmental priorities and within aff...

    Answered 8 Sept 2026

    Original Parliament record
  • Guided WeaponsMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23271More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Ground Based Air Defence, what steps is he taking to mitigate the unaffordable

    Answer: The Ministry of Defence continues to assess options to deliver the required Ground Based Air Defence capability in an affordable manner. The programme is pursuing a more incremental and adaptable approach, prioritising lower-cost and faster-to-field capab...

    Answered 8 Sept 2026

    Original Parliament record
  • MinesweepersMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23270More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Mine Hunting Capability, what are the recognised capability shortfalls.

    Answer: The National Infrastructure and Service Transformation Authority (NISTA) assess the Mine Hunting Capability programme to be affordable and deliverable. Delivery confidence continues to improve with close collaboration between the MoD, industry partners an...

    Answered 8 Sept 2026

    Original Parliament record
  • Boeing E-7Ministry of DefenceTabled 28 Aug 2026AnsweredUIN 23269More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, E7 Wedgetail, what is the extent of the schedule optimism bias that has caused

    Answer: The E-7 programme has involved considerable complexity, which influenced the schedule and was exacerbated by equipment re-design and re-certification.

    Answered 8 Sept 2026

    Original Parliament record
  • Armoured Fighting VehiclesMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23268More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Armoured Cavalry 2025, whether a re-approval is required following the Ministe

    Answer: In conjunction with General Dynamics, the Demonstration phase timetable is being considered as part of the Department's wider assessment of the programme. Future approval requirements will also be considered as part of that assessment.

    Answered 8 Sept 2026

    Original Parliament record
  • Defence: PropertyMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23267More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Defence Estate Optimisation Portfolio, which projects have been resubmitted an

    Answer: No projects within the Defence Estate Optimisation Portfolio (DEOP) have been resubmitted with a reduced scope to meet affordability targets. Affordability across DEOP has been considered through the Defence Investment Plan and subsequent portfolio review...

    Answered 7 Sept 2026

    Original Parliament record
  • LE TacCIS ProgrammeMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23266More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Land Environment Tactical Communication and Information Systems, whether the p

    Answer: The publication of the Defence Investment Plan has provided greater clarity on Defence investment priorities. The formal reset from the Land Environment Tactical Communication and Information Systems (LETacCIS) Programme to the Land Domain Command, Contro...

    Answered 7 Sept 2026

    Original Parliament record
  • Defence: TelecommunicationsMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23265More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Next Generation (Fixed) Communication Network, how far beyond the allocated fu

    Answer: At the time of the National Infrastructure and Service Transformation Authority review, the risk-adjusted schedules indicated a potential delivery timeline extending beyond the period covered by the Defence Investment Plan funding allocation. The latest s...

    Answered 8 Sept 2026

    Original Parliament record
  • TanksMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23264More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Armour Main Battle Tank Programme, what is the length of the forecast delay an

    Answer: The Armour Main Battle Tank Programme is currently subject to an ongoing review of programme performance and a related reapproval process. Under current plans, reapproval is expected during Financial Year 2026-27. As part of this work, the Department is c...

    Answered 8 Sept 2026

    Original Parliament record
  • Armed Forces: RecruitmentMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23263More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Armed Forces Recruitment Programme, which aspects of the service are not progr

    Answer: The Armed Forces Recruiting solution continues to mature in line with the required service commencement dates, and the Programme remains focused on delivery against the agreed plan. Digital and data delivery remain key programme risk areas, reflecting the...

    Answered 8 Sept 2026

    Original Parliament record
  • SkynetMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23262More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, SKYNET 6 (aka FBLOS), following the publication of the Defence Investment Plan

    Answer: The SKYNET 6 programme’s scope and budget are aligned for the duration of the current Parliament. Balance of investment assessments will continue to be made throughout the life SKYNET as operational requirements, threat assessments and priorities change.

    Answered 8 Sept 2026

    Original Parliament record
  • Unmanned Marine SystemsMinistry of DefenceTabled 28 Aug 2026AnsweredUIN 23261More

    Question: To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Future Air Dominance System, whether he has built the evidence needed to infor

    Answer: The Future Air Dominance System (FADS) programme has made substantial progress and continues to mature evidence through ongoing analysis, experimentation and concept development. These activities are designed to test operational concepts, generate evidenc...